Home
News
FAQ
Neighborhoods
Services
Government
Mayor's Office
Search
*****

Main DPW Page

Bureau of Water and Wastewater

Department of Public Works Water & Wastewater
Water & Wastewater
Solid Waste General Services

Loch Raven Dam Rehabilitation

Project Progress

This project is expected to continue through August, 2005. In general, the following timeline has been established for this project:

2004 - Spring Complete roller compacted concrete (RCC) placement - East Side

2004 - Summer Prepare site for west side RCC and East Side overflow

2004 - Fall Begin RCC Placement - West Side

2005 - Spring Complete RCC placement - West Side

2005 - Summer Apply conventional concrete face, complete site restoration

Weather's Impacts on Progress

Progress on this project is greatly influenced by the weather, and not simply because it is difficult to work in the rain. As a functioning water supply for much of the city and several neighboring counties, the project must be built without lowering the reservoir, and the Gunpowder must be allowed to flow freely over the dam as nature intends. Therefore, only one half of the dam can be constructed at a time: a 3-foot-high bulkhead has been installed to protect the work area, and the construction site at the base of the dam must accommodate the river.

Loch Raven Dam impounds rainwater from a roughly 300-square-mile watershed, so a few hours of rain can mean "water over the dam" for days. 2003's record-breaking rainfalls presented numerous challenges throughout this first year of construction.

Finally, concrete cannot be placed during periods of hard freeze. Therefore, progress on one of the most important parts of the project has to stop from December through early March.

Progress Updates

Detailed Project information and a collection of construction photographs are available through the links below.

Photo Gallery

                    
LR Dam Main Page Road and Watershed Use