Progress Photo Gallery

Loch Raven Dam Project

Photos are listed in desecending order
(Click on Picture to enlarge)


Reforestation begins – over 300 trees will be planted
throughout the construction site to replace those removed. A mix of several native species, including hardwoods
and flowering trees
are being planted.
April, 2005

Rebuilding the west side spillway crest
March, 2005

Preparing for the last of the
west side concrete…
February, 2005



With RCC placement complete, finish concrete on the west side spillway awaits warmer temperatures. January, 2005



Nearly complete,
the west side.
Non-overflow now shadows the Historic 1922 gate house.
November, 2004


With double shifts,
RCC placement on
The spillway nears completion ahead of schedule
November, 2004



Don’t blink or you’ll
Miss it!

The west side non-overflow is rising fast!!!
October, 2004


The "new" east side
September 2004


The east half...
Finished profile contrasts with the original dam
September 2004


Last anchors...
Installing the last 16 anchors in the west side spillway
September 2004


rcc placement flies up the west side non-overflow
September 2004


The "new" Loch Raven Dam is almost complete on the
east side.
August 2004


Climbing "up the ladder" at work???
August 2004


Conventional concrete is placed over the RCC as a smooth surface on the spillway. This surface will resist wear from the aggressive friction of water flowing over the dam.
July 2004


Hundreds of pieces of reinforcement bar (rebar) were set when RCC was placed on the spillway. This rebar will hold the finish surface of concrete in place.
July 2004


The east-side non-overflow section is now higher than ever before.
June 2004


East-side non-overflow section begins to take shape
May 2004


With the early march thaw, RCC placement takes off.
March 2004


By the official start of spring, RCC placement on the east-side spillway is nearly complete.
March 2004


Excavation of the west side continued through the winter
January 2004


East Side RCC Placement
November 2003


East Side RCC Placement
November 2003


Excavation reveals underlying bedrock
September 2003


Bedrock must be thoroughly cleaned for proper concrete placement
September 2003


Rains continue to wreak havoc on the construction site.
August 2003

Excavation continues down the east side abutment to the toe of the 1912 structure. White outlines depict where new concrete will be added to the dam.
August 2003

Unusually heavy June rains flooded the work area.

Significant snow and rain since last fall have filled the City's reservoirs to 100% capacity. Loch Raven's "island" is an island again for the first time in several years.


As April showers continue well into May, the Gunpowder River rushes through the construction site, yet progress continues: rock anchor installation on the east side is nearly complete.

Geotechnical engineers from across the region tour the site, and examine rock anchor installation first-hand -
April 2003

Workers must guide the end of the cable by hand into the drilled opening

Crane is used to raise 2.5 ton steel cable anchor for installation

12-inch diameter drill bit is used to core into the dam, up to 159 feet deep

Rain and snow melt raise the reservoir level above crest - January 2003

Removal of Shotcrete Facing

Before Construction
July 2002